We began working on the 26-acre Western Expansion Landfill final cover system late this summer. We are working long hours to get this landfill covered with liner and the necessary soil for winter stabilization. With steep slopes that range over 600’ in places, this project has its challenges. We have over a third of the soil in place, as well as over half of the liner in place as well. The second portion of this project consist of installing liner, road work and stormwater controls on a 25-acre portion of the Western Expansion Landfill. The third portion of this project is a final cover system over a 28-acre portion of the Southeast Landfill on this site. This work will begin in the spring of 2017. With all of the challenges on this project, the crews are doing a great job keeping health and safety and production in mind. Once completed, this will project will help the owner contain the gases needed for power production, as well as keep the landfill odors down.