Mitchell Mill Road Widening


Overview

This project consists of approximately 6000 feet of road widening broken into 3 phases and to span a period of 600 days. This widening is taking place in an extremely high traffic area and safety is of the essence. The project is also covered with overhead and underground utilities that will make all aspects of this project a challenge. The Phase 1 operations started July 11th and are well under way. The erosion control and 75% of the grading for Phase 1 are complete to date. Storm, sewer and water operations are slated to start September 19th with nearly 750 linear feet of box culvert to start being set shortly after that. Phase 1 paving should be well under way by year end. Phase 2 operations are scheduled to start in early spring of 2017.